Data center to Azure with no cutover window.
Situation
A manufacturer with a data center contract ending in five months, 140 virtual machines and an internal team of three. Nobody wanted to sign the cutover date.
What we did
Two-week diagnostic; hub-and-spoke landing zone; four waves ordered by dependency, each with a restored backup and rehearsed rollback; night windows agreed with the plant.
Result
Full migration in eight weeks without stopping operations. The internal team got its evenings back by week two, and the monthly cost has been reviewed in writing ever since.